P & ID Check List

by Piping Engineer on January 10, 2009 · 2 comments

The following shall be considered in P & ID Check List -Verify revision, purpose of revisions, numbering, title. -Verify notes reference drawings (including Removal P&IDs) -Verify “holds” are indicated -Verify piping spec break -Verify line number, cross check with line schedule and sizing -Verify all sizes are indicated and match the process calculations : control [...]

Following items taken into account 1. Has data from the design basis been utilized in the calculations ? 2. Are applicable references identified and supplied? 3. Are relevant input data and assumptions clearly listed? 4. Are the applicable regulations, codes, standards and specifications utilized listed within the calculation data & clearly stated in the report? [...]

Following items taken into account 1.Technical Content -Verify scope of work in document with project requirements / CTR. -Verify technical contents in compliance with design basis/premise. -Verify technical contents compliance with contract/client specifications. -Verify technical contents in compliance with appropriate regulatory and statutory requirements, which are identified and accurately referenced. -Verify assumptions and methodology adequately [...]

MTO PHASE Are the following aspect correct: 1.Contractual Drawings / Requirements 2.Mark-up of P&ID’s completed 3.Mark-up of line list completed 4.Mark–up of Layout / General Arrangement completed 5.“ HOLD” List 6.Following special items taken into account -Utilities stations -Eye wash & stations -Safety equipments -Insulation -Hydrostatic vents / drains -Motorised valves (MOV, BDV, ESDV,…) -Sample [...]