MTO PHASE
Are the following aspect correct:
1.Contractual Drawings / Requirements
2.Mark-up of P&ID’s completed
3.Mark-up of line list completed
4.Mark–up of Layout / General Arrangement completed
5.“ HOLD” List
6.Following special items taken into account
-Utilities stations
-Eye wash & stations
-Safety equipments
-Insulation
-Hydrostatic vents / drains
-Motorised valves (MOV, BDV, ESDV,…)
-Sample connections
-Inline instrument material
-Piping on vessels/ tanks
-Filter
-Flexible hose
-Hose connectors
-Expansion Bellows
-Access fittings
-Flame arrestor
-Bird screen
-Barred tee
-5/10 Elbows
-Sight glass
-Bolting for spectacle blind, butterfly valves,…
7.Contingencies considered