Piping Arrangement Around Drum

by Piping Engineer on December 7, 2008

Piping Arrangement Around Drum

1.Uses

-Collect liquid from vapor circuits and pump it to other process group
-Disposal
-Product storage
-Steam generation
-Deaeration of boiler feed water

2.Steps in preparation piping arrangement around drums

-Setting height of the drum
-Study of nozzle orientation
-Platforming
-Piping Arrangement

3.Location of Drums

-Adjacent to related equipment
-As a standalone operation
-Vertical drums are arranged on the same center-line of vertical equipment

4.Installation of Drums

a.Factors

-Function of drums
-Process requirement
-Shape and size of drum
-Cost effectiveness

b.Elevation and Support

-NPSH
-Minimum clearance
-Common platforming
-Maintenance and operator access

5.Nozzle orientation

a.Basic Conception

-To meet the process requirement
-Easy operation
-Easy maintenance
-Cost effectiveness

b.Nozzles and accessories installed in Access Area

-Manhole, Hand hole and Access hole
-Instrument nozzles: LC,LG,PG,etc.
-Purge nozzles (N2, Steam)
-Nameplate
-Davit

c.Nozzle installed in Piping Area
-Nozzles to which piping is connected
-Required at drums for access to valves, instrument and blinds
-Maintenance accesses

6.Piping Plan

a.Piping are arranged according

-Conjunction with nozzle location
-Platform arrangement
-Drums location to related equipment

b.Support

-Saddles from concrete piers
-Steel frames
-Trunnions

drum_vertical_grnd_label

drum_horizontal_struc_label
drum_horizontal_ground_label

Bookmark and Share:
Share This Post

Related posts

{ 1 comment… read it below or add one }

R Seeralan December 8, 2008 at 4:37 am

Hi,
It is realy nice….
I am working in India as Pipe Stress Engineer(CAESAR II).
If any recurtment in your organisation means Pls let to me.
Because I am willing to work in Singapore such as your organisation.

Thanks and Regards,

R Seeralan
Mobile : +91 98841 29850

Leave a Comment

CommentLuv Enabled

Previous post:

Next post: