The following shall be considered in Design Information to other sections
1.For Civil Section
-Pipe Rack Width, height and Loading.
-Structure for Equipment.
-Equipment Height.
-Sleeper.
-Special Pipe Support.
-Routing Plan of Instrument cable duct and Electric cable duct.
2.For Equipment Section
-Platform Design for the Column.
-Pipe Support Lug for the Column.
-Nozzle Orientation of the Column.
-Platform Design for the Drum.
-Nozzle Orientation for the Drum.
3.For Instrument Section
-Match line of engineering and material purchase between Piping and Instrument section for each instrument equipment.